| Projects
Phase I - Debris Removal: Work consisted of removing and
disposing of the top layer of debris on the beach. Hemphill Construction
Company collected a total of 33,611 cubic yards for a total project
cost of $ 692,388.
Phase II - Debris Removal: This project required the retrieval
of all sand to a depth of 12" and sifted through a mesh screen
to collect the building fragments and small debris not collected
as part of Phase I. Necaise Brothers Construction Co. completed
this work at a cost of $ 6,643,800.
Phase III - Debris Removal: Holden Earth Moving and Construction
Co removed large concrete structures that were not accessible during
the Phase I project at a cost of $ 36,210.
Phase IV - Debris Removal: Crews from the Sand Beach Authority
continued to remove debris from the shoreline until the U.S. Coast
Guard completed the Near Shore Debris Removal Project. Once completed,
Sand Beach crews made a final pass with our beach cleaning equipment
to complete the last phase of the debris removal process. The cost
to complete this phase was $242,507.
Beach Profile Project: Phase II of the debris removal project
left rows of cleaned sand after it was sifted. Sand Beach Crews
mechanically reshaped the beach and removed the blown sand against
the seawall to reestablish the normal beach grade. This work utilized
our own equipment and cost's associated with said work was $ 165,005.
Boardwalk: Brown and Mitchell, Inc a local engineering firm
hired by the Board of Supervisors has completed the plans and specifications:
which includes a concrete replacement of the timber boardwalk. The
project has been advertised to receive bids with the Bid Opening
scheduled for April 15, 2008.
Beach Renourishment: The U.S. Army Corp of Engineers has
employed Enco Dredge Co. to complete the repairs of the damaged
seawall, culverts, equipment ramps and replace approximately 890,000
cubic yards of sand.
Beach Parking Lots:
- Courthouse Rd
Most of the repair is completed with only the streetlights and
approximately 160' of sidewalk installation remaining to be completed.
Projected completion date May, 2008.
- Long Beach Comfort Station
Bids were received February 12, 2008. Finalizing details with
MEMA of an expansion project for this site. Project scheduled
to begin May, 2008.
- Jeff Davis Parking Lot
Plans and specifications have been submitted to MEMA for review
and we are waiting on final approval to proceed with advertising
to receive bids.
- Pass Christian Comfort Station Parking Lot
The Board of Supervisors hired the engineering firm of Moran and
Machado, PLLC to develop plans and specifications for said repair.
- Preservation Oaks Parking Lot
Plans and specifications are being finalized by Moran and Machado,
PLLC to submit to MEMA for final review.
Jim Simpson Pier: Plans and specifications have been submitted
to MEMA for review and we are waiting on final approval to proceed
with advertising to receive bids.
Sand Fence: Sand Beach Authority personnel have been installing
sand fence in areas along the beach. To date, crews have completed
9,270 lf of the 48,400 lf required to complete this project. Total
estimated cost to replace all of the damaged fencing is $ 109,556.
Welcome to Biloxi Sign: With the near completion of the
Biloxi/Ocean Springs Bridge on Hwy 90, Sand Beach employees have
begun repairing the signs. Work to date has involved the removal
of all the damaged areas; replacement of concrete boards and the
placement of stucco should begin in the near future. Anticipated
completion of the project is May 2008.
Comfort Station: Although their replacement are the responsibility
of the Coast Transit Authority, we are working closely with them
to see that these restroom facilities are rebuilt along our beach
front. Currently, efforts to resolve the elevation issues are being
addressed with FEMA and we are hopeful that the reconstruction will
begin soon.
|